Utilization and profit

Tracking a Fixed-Fee Project Before It Runs Over

Sam&Sain Co. · Published · Updated · 7 minute read

Project budget tracking is the weekly comparison of each phase’s hours spent with the hours its fee allows and with how complete the work is. A fixed-fee project rarely goes over loudly, and this check catches it while there is still time to act.

On this page

Terms Used

  • Phase budget: the hours a phase’s share of the fee pays for.
  • Blended rate: the average hourly rate of the people who will do a phase, weighted by their hours.
  • Percent complete: how much of the phase’s work is done, estimated from its deliverables.
  • Earned value: the share of the budget that the completed work is worth.
  • Performance index: earned value divided by the value of the time spent; below 1.0 means the phase is running over.

Turn the Fee into Hours

A fee is a budget of hours in disguise. Before the project starts, divide each phase’s share of the fee by the blended hourly rate of the people who will do it. That number, written down at the start, is what every later check compares against.

Example, round numbers: a $100,000 feeFeeBlended rateHours allowed
Concept$20,000$160125
Detailed design$50,000$125400
Tender and contract administration$30,000$150200
Total$100,000725

Budget by phase, not only for the whole project. A project-wide budget lets an overrun in design hide inside hours that contract administration hasn’t used yet, until contract administration starts and there are none left.

Hold some back. For example, plan the design phase to 90% of its hours: 360 hours planned, and 40 in reserve, so that one surprise does not put the phase over. Spend the reserve only with the project manager’s say-so, and record what it went on.

Three Numbers, Every Week

  1. Hours spent on each phase, from the week’s timesheets.
  2. Percent of budget spent: hours spent ÷ hours allowed.
  3. Percent complete: the project manager’s estimate of how much of the phase’s work is done.

When percent spent runs ahead of percent complete, the phase is heading over. For example, a phase that is 50% complete with 65% of its hours gone will need about 130% of its budget at the same pace (65 ÷ 50).

Earned Value, Simply

Earned value puts the same check in dollars, which lets you add phases and projects together.

  • Earned value = budget × percent complete. For example, a $40,000 phase that is 50% complete has earned $20,000 of its fee.
  • Time spent = the hours spent so far, valued at the same rates used to build the budget. Say $26,000.
  • Performance index (in earned value terms, the cost performance index) = earned value ÷ time spent. Here 20,000 ÷ 26,000 = 0.77.
  • Estimate at completion = budget ÷ the index. Here 40,000 × 26,000 ÷ 20,000 = $52,000 of time.

An index below 1.0 means each dollar of time is producing less than a dollar of planned work. In this example, if nothing changes, the phase will use about $12,000 more time, at the budget’s rates, than its fee pays for. That is fee the firm cannot bill: written off at the end, or raised with the client if the scope grew. What the overrun costs the firm in cash depends on the salary cost of those hours, which is lower than their billing value.

The method works the same with salary cost instead of billing rates, as long as the budget and the time spent are valued the same way.

Make Percent Complete Honest

Earned value is only as good as the percent complete. Three habits help:

  • Base it on deliverables, not hours. For example, “6 of 10 drawings issued for review” is harder to guess than “about 60%”.
  • Weight the deliverables by effort. For example, if a report takes half the phase’s work and eight drawings the other half, the report finished alone is 50% complete, not one ninth.
  • Ask for it every week, from the person doing the work, and keep the history. For example, an estimate that sits at 90% for a month is a warning in itself.

Never work percent complete out from hours spent. For example, a phase that has used 60% of its hours is not 60% complete because of it; that sum only repeats the budget back and hides the overrun the check exists to find.

A One-Page Weekly Report

The whole check fits on one page: one row per live phase, sorted with the lowest index first.

ExampleHours allowedHours spentSpentCompleteIndexThis week
Project C, contract administration20017085%60%0.71Decide: scope or plan
Project A, detailed design40022055%50%0.91Watch
Project B, concept1256048%60%1.25On track

Here the index is percent complete divided by percent spent. It gives the same answer as earned value only while the hours spent carry the mix of rates the budget assumed; if senior people did more of the hours than planned, value each person’s hours at their role’s budget rate and use the dollar index instead. The partners read the top rows; the rest need nothing from them. Our article on engineering firm KPIs shows where this page sits beside utilization and unbilled work.

When a Phase Is Heading Over

Decide in the same week. There are only a few choices:

  • The scope grew. Raise it with the client as additional services, in writing, before more hours are spent.
  • The plan was wrong. Change the staffing or the approach for the rest of the phase, and record why, so the next fee is better.
  • The work was underpriced. Finish it well, and use the closed project’s hours to price the next one. This is how a firm learns which kinds of work pay; see fixed fee or hourly.

Hourly Projects Need Tracking Too

An hourly project can’t run past its fee the way a fixed fee can, as long as its rates cover the firm’s costs; rates set below cost lose money on every hour, which our article on setting hourly rates covers. Hourly projects have budgets of their own too. A not-to-exceed amount or an upset limit caps what the firm can bill, so hours past it are lost just as on a fixed fee. And a client who sees an invoice well above the estimate they were given is a client who disputes it, which shows up as lower realization. Track hourly projects against their estimate the same way, and warn the client before the limit, not after.

Close Each Project Out

When a project ends, put its final hours by phase beside the hours allowed, and write one line on why each phase landed where it did. Five minutes per project builds the firm’s best pricing record: the next fee for the same kind of work starts from what the last one actually took. Our article on pricing engineering services uses that record.

What the Industry Reports

Deltek’s 2026 study of architecture and engineering firms found 75% of projects on or under budget and 40% of projects falling behind schedule (Deltek, 26 May 2026). Put the other way round, a quarter of projects went over budget. A weekly hours-against-fee check is the cheapest way to know which quarter your projects are in.

Common Budget Tracking Mistakes

  • Late timesheets. A check run on half the week’s hours says everything is fine.
  • One budget for the whole project. Early phases borrow hours from later ones without anyone deciding to.
  • Percent complete from hours spent. It repeats the budget back and hides the overrun.
  • Spending the reserve first. The contingency is for surprises, not for the first week.
  • Checking at invoicing. By then the hours are spent, and the only choice left is a write-off.

A Checklist for Project Budgets

  1. Turn each phase’s fee into hours at a blended rate, before the project starts.
  2. Hold back a reserve, and record what it is spent on.
  3. Close timesheets on the same day each week.
  4. Collect percent complete from deliverables, weighted by effort.
  5. Put every live phase on one page, sorted by index.
  6. Decide on each phase below 1.0 in the same week.
  7. Track hourly projects against their estimate and limit.
  8. Close each project out with its final hours and one line per phase.

How We Approach This

Without a weekly check, an overrun shows up when the invoice goes out. Our performance work puts each project’s hours and margin in front of you every week, while there is still time to act: hours against fee, every week, for every live project.

Questions

How Do You Track a Project Budget?

Turn the fee into hours for each phase, then each week compare the hours charged with the hours allowed and with how complete the phase is.

What Is Earned Value?

Earned value is the share of the budget the completed work is worth. For example, a $40,000 phase that is 50% complete has earned $20,000 (40,000 × 0.5). If $26,000 of time has been spent, valued at the budget’s rates, the phase is running over.

How Do You Estimate the Cost at Completion?

Divide the budget by the performance index. For example, a $40,000 phase with an index of 0.77 will use about $52,000 of time if nothing changes (40,000 ÷ 0.77).

How Often Should Project Budgets Be Reviewed?

Every week for live projects. A monthly review finds an overrun four weeks later, when less can be done about it.

How Do You Measure Percent Complete?

From deliverables, weighted by the effort each one takes, and never from hours spent. Ask the person doing the work every week, and keep the history.

Sources

Updates

  • : Rewritten at full length: a worked phase budget, weighting percent complete, a one-page weekly report, hourly projects, closing projects out, common mistakes and a checklist; Deltek’s figures re-read.