Utilization and profit

Engineering Firm KPIs: The Numbers Partners Should See Every Week

Sam&Sain Co. · Published · 3 minute read

A month-end report arrives after the hours are spent. A one-page weekly scorecard shows trouble while there is still time to act.

On this page

Weekly or Monthly

A KPI is only useful if someone can act on it before it is too late. So split the numbers by how fast they move. The weekly ones are about this week’s hours and projects. The monthly ones are about the firm.

Every Week

KPIHow to calculate itWhat it warns you about
Utilization, by person and teamBillable hours ÷ paid hours, against each person’s targetPeople short of project work, or time going somewhere unplanned
Hours against fee, by live projectHours charged ÷ hours the fee allows, beside percent completeA project running over while there is still time to act
Unbilled workValue of work done and not yet invoicedCash tied up in work the client has not been asked to pay for
Next weeks’ loadPlanned hours ÷ available hours, from the resource planDeadlines at risk, or a gap to fill with new work

Every Month

KPIHow to calculate it
Net multiplierNet revenue ÷ direct labour
RealizationFees billed ÷ value of hours at standard rates
Overhead rateIndirect costs ÷ direct labour
Days to collectAccounts receivable ÷ average daily billings
BacklogSigned fees still to earn ÷ average monthly fees, in months
Win rateProjects won ÷ proposals decided, by count and by value
Operating profitRevenue less operating expenses, on total and on net revenue

Each has its own article: multipliers, realization, overhead rate, unbilled work and win rate.

One Page, One Meeting

The weekly numbers belong on one page, read in fifteen minutes by the partners and project managers on the same day each week. Three rules keep it useful:

  • Every number has an owner. The project manager owns hours against fee; a partner owns utilization; whoever invoices owns unbilled work.
  • Every number has a trigger. Decide in advance what happens when a project passes 80% of its hours, or unbilled work passes two weeks of fees.
  • The page builds itself. If someone spends half a day each week assembling it, it will stop. The numbers should come straight from the timesheet and accounting systems.

Why the Weekly View Matters Now

Deltek’s 2026 study found 75% of projects on or under budget but 40% behind schedule, and called for project managers to have real-time visibility of schedules, resources and performance (Deltek, 26 May 2026). A weekly page is the simplest way to get there.

What to Leave Off

Anything nobody acts on. A KPI that has not changed a decision in three months can move to a quarterly review. A short page that is read beats a long one that is filed.

We build exactly this page as part of our operation and performance work: a weekly scorecard of utilization, project budgets and unbilled work, and a monthly review with the partners.

Questions

What KPIs Should an Engineering Firm Track?

Utilization, realization, the net multiplier, the overhead rate, project hours against fee, unbilled work in progress, days to collect, backlog and proposal win rate.

How Often Should KPIs Be Reviewed?

The ones the team can act on this week (utilization, project budgets, unbilled work) every week. The ones that move slowly (multiplier, overhead, win rate) every month.

What Is Backlog?

The fees still to be earned on signed work. Divided by the monthly fees the firm earns, it says how many months of work are secured.

Sources: Deltek, 47th Clarity Architecture & Engineering Industry Study, 12 May 2026.