Resource Planning at an Engineering Firm: Who Works on What Next Week

Sam&Sain Co. · Published · Updated · 7 minute read

Resource planning at an engineering firm answers one question each week: who is working on what, and who has room. Firms that answer it from memory find out about a clash when a deadline slips.

On this page

Terms Used

  • Capacity: the hours a person or team can give to projects in a week, after leave and the non-billable work their role owns.
  • Planned hours: hours put against a project for a person and a week.
  • Open hours: capacity not yet planned on anything.
  • Backlog: signed work not yet done, in hours or fees.
  • Tentative work: pursuits not yet won, counted at their chance of winning in the rough plan.

The Question It Answers

Resource planning answers one question every week: who is working on what, for how many hours, and who has room. At a firm of a dozen people, the partners often answer it from memory. That works until two deadlines land in the same week, a designer sits idle waiting for input, or the firm says yes to a project nobody has time for. A written plan turns those surprises into something seen weeks ahead, while dates and staffing can still change.

Capacity: The Sum Behind the Plan

Capacity is the hours each person can put on projects in a week, once the week’s other work is taken out. Project capacity = hours at work − routine non-billable time − planned non-billable pieces. A designer at work 40 hours who keeps 8 for meetings, administration and training has 32 hours for projects (40 − 8 = 32); in a week with an 8-hour proposal, 24 (40 − 8 − 8 = 24); in a week with a day of vacation, 24 again (32 − 8 = 24). Routine time differs by role, and a role’s utilization target is a guide to it; see utilization targets by role.

Example, round numbers: a team of fiveWeek 1Week 2Week 3Week 4
Hours at work, after leave200192168200
Routine non-billable time, 8 a person40404040
Planned non-billable pieces (proposals, training)08016
Project capacity160144128144
Planned on signed projects1461529680
Open hours (capacity − planned)14−83264

In this example, week 2 is over by 8 hours, so something moves now; week 3 has a vacation in it and still has room; week 4 has 64 open hours, a reason to chase work or bring a pursuit forward today.

A Plan That Fits on One Screen

The simplest useful plan is a grid: people down the side, weeks across the top, and in each cell the hours or half days planned on each project.

PersonWeek 1Week 2Week 3Week 4
Designer AProject 12: 32 hProject 12: 24 h, Project 15: 8 hProject 15: 32 hOpen: 32 h
Engineer BProject 12: 24 h, Proposal: 8 hProject 14: 32 hProject 14: 32 hProject 14: 16 h, Open: 16 h

In this example each person is at work 40 hours a week and keeps 8 for the routine non-billable work of their role. The other 32 go to projects, and to large non-billable pieces put in the plan so they are not squeezed out, like Engineer B’s 8-hour proposal in week 1, which leaves 24 hours for Project 12.

How Far Ahead

  • The next two to four weeks, in detail. By person and project, in hours or half days.
  • The next few months, roughly. By team, from the backlog and the pursuits likely to be won.

Planning further in detail is rarely worth it; projects move too much. In the rough plan, count each pursuit at its chance of winning. For example, a 400-hour pursuit the firm expects to win two times in five counts as 160 hours (400 × 0.4) until it is decided. Added up across the pursuit list, those hours show whether the next quarter needs a hire, a subconsultant or more selling.

A Weekly Rhythm

  1. Compare last week’s plan with last week’s timesheets. Where they differ, ask why. The answers show where time goes that nobody planned.
  2. Update the next four weeks. With each project manager’s needs, deadlines and leave.
  3. Resolve clashes now. Move work, bring in help, or talk to a client about a date, this week rather than in the week of the deadline.
  4. Look at the gaps. Open hours three weeks out are a reason to chase work now.

Fifteen minutes with the project managers, on the same day each week, can be enough. The comparison in the first step matters most: a plan that is never checked against the hours actually worked drifts away from the firm it describes.

Before Saying Yes to New Work

Every new project needs a name beside it. Before the proposal goes out, check the plan: who would do it, when, and what moves if it is won. The check shows a clash between the new work and the work already planned while the dates and the staffing can still change. It also belongs in the go/no-go decision: a pursuit the firm could not staff if it won scores low, however attractive the client.

Overtime and Ontario’s Rules

A plan that only balances by running people past their week should be read as a warning, not a solution. Ontario’s Employment Standards Act treats roles differently:

  • Engineers and engineering students. Ontario lists daily or weekly limits on hours of work and overtime pay among the standards they are not entitled to (Government of Ontario, exemptions for professionals). The employment contract and the firm’s policy set what applies.
  • Other staff, such as technicians, technologists and administration, unless another exemption applies. For most employees, “overtime begins after they have worked 44 hours in a work week”, and “Overtime pay is 1½ times the employee’s regular rate of pay” (Government of Ontario, overtime pay). The same page explains averaging agreements, which can spread the count over up to four weeks.

Overtime is owed on hours actually worked, not hours planned. A covered technician who works 50 hours in a week, with no averaging agreement, is owed overtime pay for 6 of them. An engineer has no statutory overtime pay, but the employment contract or the firm’s policy may give extra pay or time off, and a run of 50-hour weeks costs the firm in the weeks that follow either way. A plan shows both before they happen. This is general information, not legal advice; check each role’s status and contract against the Act.

What It Protects

  • Utilization. Fewer idle hours between projects and less waiting for input.
  • Deadlines. Clashes seen weeks ahead. Deltek’s 2026 study found 40% of projects behind schedule, and warned that limited visibility into schedules and resources quietly erodes profit and client satisfaction (Deltek, 26 May 2026).
  • People. Fewer weeks of unplanned overtime, which matters for keeping your engineers.

Tools

A spreadsheet works for a small firm, as long as it is updated weekly and kept to one version. Many project and time systems include resource planning; the advantage is that planned and actual hours sit side by side, so the weekly comparison takes minutes instead of an afternoon. Whatever the tool, it needs the same three inputs: each person’s capacity, the planned hours by project and week, and last week’s actual hours. See choosing project and accounting software.

How We Approach This

Utilization and capacity, billable time by person and team and who has room for the next project, are part of our performance work.

Questions

What Is Resource Planning in an Engineering Firm?

Planning which people work on which projects, and for how many hours, over the coming weeks, so deadlines are met and nobody is idle or overloaded.

How Do You Calculate Capacity?

Take each person’s hours at work that week, less the routine non-billable time of their role and any planned pieces such as a proposal, then add up the team. 40 hours at work less 8 routine leaves 32 for projects (40 − 8 = 32).

How Far Ahead Should a Firm Plan?

In detail for the next two to four weeks, and roughly for the next few months from backlog and likely wins.

What Is the Difference Between Resource Planning and Scheduling?

A project schedule says when each task happens. A resource plan says who does it, across all projects at once.

Who Should Own the Resource Plan?

One person, often a partner or whoever runs operations, who updates it after the weekly meeting. Project managers ask for people through the plan rather than directly, so clashes surface in one place.

Do Engineers in Ontario Get Overtime Pay?

Not under the Employment Standards Act: Ontario lists overtime pay among the standards engineers and engineering students are not entitled to, though a contract or firm policy may give extra pay or time off. For most other employees, overtime begins after 44 hours worked in a week, at 1½ times the regular rate.

Sources

Updates

  • : Rewritten at full length: the capacity sum with a worked four-week example, pursuits counted at their chance, staffing in the go/no-go, Ontario’s overtime rules on hours worked (ESA pages read) and tools; Deltek re-read.